CN'R Lawn N' Landscape - Spring CleanupsSpring Clean (N' Spring Gutter Cleaning) Updates

CN'R Lawn N' Landscape - Spring Lawn Clean UpLatest Updates

Spring Cleans / Lawn De-thatching / Spring Gutter Cleaning:

 

**the next update will likely be posted on or around April 23rd**
Please EMAIL CRAIG if you have any specific questions you need answered until then

UPDATED SUNDAY, APRIL 13, 2025:

We did a “soft start’ for spring clean ups and lawn de-thatching on Wednesday, April 9th. This was right on average of “average start date” for spring clean up and de-thatching. We called it a soft start, with less workers in….work out the kinks in our equipment, etc. Thereafter, it went pretty well the rest of that week. C N’R crews did work the following Thursday, 4/10 and Friday, 4/11.

We expect this service to last for the week of April 14th, and through the full week of April 21st. Our target end date for spring clean up and lawn de-thatching is Friday, April 25th. At the time of this update, long way to go to reach that target date, and weather between now and then will play a big role.

If you are signed up for spring gutter cleaning, we are completing some jobs as we progress through our spring clean up service. But, not all will get done over the next couple weeks, and whatever gutter cleaning jobs we do not finish by the target date of April 25th mentioned above, then we will complete these jobs late April or early May.

Any further questions, please EMAIL CRAIG. Otherwise look for our next update to be posted sometime around April 23rd.


 


CN'R Lawn N' Landscape - Minnetonka, Eden Prairie
 Past Updates

**the next update will likely be posted on or around April 23rd**
Please EMAIL CRAIG if you have any specific questions you need answered until then

UPDATED SUNDAY, APRIL 13, 2025:

We did a “soft start’ for spring clean ups and lawn de-thatching on Wednesday, April 9th. This was right on average of “average start date” for spring clean up and de-thatching. We called it a soft start, with less workers in….work out the kinks in our equipment, etc. Thereafter, it went pretty well the rest of that week. C N’R crews did work the following Thursday, 4/10 and Friday, 4/11.

We expect this service to last for the week of April 14th, and through the full week of April 21st. Our target end date for spring clean up and lawn de-thatching is Friday, April 25th. At the time of this update, long way to go to reach that target date, and weather between now and then will play a big role.

If you are signed up for spring gutter cleaning, we are completing some jobs as we progress through our spring clean up service. But, not all will get done over the next couple weeks, and whatever gutter cleaning jobs we do not finish by the target date of April 25th mentioned above, then we will complete these jobs late April or early May.

Any further questions, please EMAIL CRAIG. Otherwise look for our next update to be posted sometime around April 23rd.


UPDATED APRIL 3, 2025:

Here we are on April 3rd, and we just received a bit of a snowfall which may delay things a bit (it is melting fast), but we are still optimistic of starting on time. What does on-time mean? Well, average start time for spring clean up and lawn de-thatching is sometime between about April 5th & April 11th, and at the time of this update our target start date is April 9th or 10th. Barring anymore weather delays, hopefully we can get going. And if it starts on or around the 10th, it should take us about 2 weeks to get all clean ups and lawn de-thatching done. If you have not signed up yet and you are a new or existing customer reading this, please move quickly to get on our schedule before it is too late. As always, this is all weather depending, but we will likely be cutting off any new work by around the 21st of April.

FREE ESTIMATES  always available for NEW customers. We have room to service new customer!
Please submit your request at FREE ESTIMATES

HOW ABOUT SPRING GUTTER CLEANING? The plan at this time is to complete gutter cleaning jobs as we progress through spring clean ups and lawn de-thatching. If you are signed up for both spring clean up and gutter cleaning, it is likely we will complete both jobs on the same visit - but sometimes it does not happen that way. Just depends on scheduling, weather, and other items.

Always feel free to reach out to CRAIG with any further questions. We will keep you posted!


UPDATED MARCH 19, 2025

Spring Clean Ups & Lawn De-thatching on average start sometime in that April 5th & April 11th time frame. Sometimes we start a little earlier, but more often (as of late) we have been starting later than that date range.

This spring, so far, looks like an “on-time” start. This can change fast. Yes, there is possibility of starting a bit early, so if you are a current customer, please be sure to fill out your service renewal forms so we have you confirmed on our schedule.

For new customers, please go to FREE ESTIMATES to submit your request and we will get pricing to you as soon as possible. We appreciate the opportunity!

Spring gutter cleaning? At this time, we do not have a plan for this, but typically we will complete these jobs mid-April - mid-May. Stay tuned for more info.


 


CN'R Lawn N' Landscape - Minnetonka, Eden Prairie